Power Outage in Atascadero
Updates from PG&E
9:06 a.m.
Started | Wednesday, May 20, 2015 @ 9 a.m. |
Customers affected | Eight |
Cause | Planned maintenance in the area. |
PG&E status | PG&E repair crew is on-site working to restore power. |
Estimated time of restoral | Wednesday, May 20, 2015 @ 4 p.m. |
7:01 p.m.
Started | Wednesday, Jan. 27, 2021 @ 7 p.m. |
Customers affected | 17 |
Cause | Our preliminary determination is that your outage was caused by the weather. |
PG&E status | PG&E has assigned a crew to assess the outage. |
7:26 p.m.
PG&E status | Power restored. |