Press release from the City of Arcata:
Site cleanup is set to begin on the area affected by the Downtown Fire.
The demolition and removal of fire debris near the corner of 10th and H Street can now proceed following the recent release of the site to the property owners by insurance companies. This milestone allows cleanup and recovery activities to move into the next phase.
The City has been working closely with the property owners to identify a qualified contractor to complete the site cleanup and to help streamline the permitting process with the various regulatory agencies involved in the project.
The cleanup effort is particularly complex because the damaged structures and debris crossed multiple property lines during the fire event. As a result, all affected properties must be cleaned and managed together as a single coordinated project. The City appreciates the cooperation and diligence of the property owners who have worked collaboratively to move the project forward and complete the cleanup effort as one unified project. For a project such as this, it is typical to take approximately four weeks for the contractor to mobilize and approximately four weeks to complete the work depending on specific site conditions.
The selected contractor is expected to visit the site next week to review the site conditions, develop a detailed work plan and meet with permitting and regulatory agencies prior to mobilization. The City will share the project timeline with the public when it is available, so that community will know when the work will begin and when the project is expected to be completed.
Cleanup operations will involve the removal of fire-damaged materials and debris from the site and loading it on to trucks for disposal out of the area. When construction begins, community members should expect intermittent traffic disruptions in the downtown area during the work to accommodate truck loading, hauling activities and construction equipment operations. Traffic control measures will be implemented to help maintain public safety and minimize impacts whenever possible.
The City appreciates the patience and cooperation of the community, property owners and partner agencies as this work moves forward. Additional updates will be provided as more information becomes available. For immediate questions, please contact the City Manager’s Office at (707) 822-5953.