Gillen Tener Martin / @ 1:25 p.m. / Agendizer

Eureka Planning Commission to Consider Reversing Design Committee’s Denial of Fiveplex on Buhne After Housing Advocates Threaten Litigation. Plus: Eureka’s Waterfront RV Park!

From the staff report: Location of the proposed five-plex.

In a special meeting tomorrow evening, the Eureka Planning Commission will revisit Adams Commercial General Contracting (ACGC) Inc.’s proposed five-plex on Buhne Street.

If approved, ACGC’s proposal would develop a vacant 9,000-square-foot parcel near the corner of West Buhne and Garland Streets into five units – one one-bedroom, three two-bedroom and one three-bedroom – each with their own garage.

The Design Review Committee previously denied the project in its May 8 meeting, citing public comment the City received from neighbors concerned with potential losses of privacy and sunlight.

“The proposed complex will permanently take away western sun that has been unobstructed for 132 years,” West Buhne property owner Dan Reid wrote to the City in a May 7 email, referring to potential shading impacts on his 1892 Queen Anne Victorian home.

Other letters voicing worries about light loss stressed the mold-prone nature of the Victorians the neighborhood is speckled with, and some forwarded to the City by Reid included a real estate professionals’ opinions that the placement of ACGC’s proposed development would reduce his property’s value.

“Due to the applicant’s representative expressing inflexibility to work with the surrounding neighbors to address neighborhood concerns and potential sunlight/shading issues of the project on the adjacent neighbor’s property, the Design Review Committee finds proposed development to be detrimental to public health and safety,” the Committee’s rejection resolution stated.

On May 16, ACGC filed an appeal of the Design Review Committe’s denial, and on May 17 ACGC Real Estate Development Director & Community Liaison Raelina Krikston sent a letter to the City stressing the quality of the project’s construction and aesthetics, its compliance with Eureka’s zoning and regulations and the ways in which the five units would contribute to local housing needs.

“Ensuring a commitment to maintaining the quality of life for all residents, whether they rent or own, underscores the project’s dedication to fostering a harmonious and inclusive community,” Krikston wrote.

Krikston’s letter also pointed to the project’s alignment with California’s Housing Accountability Act (HAA), which restricts local agencies in their abilities to deny housing projects that meet “objective” local planning standards – “objective” meaning “involving no personal or subjective judgment by a public official and being uniformly verifiable by reference to an external and uniform benchmark or criterion available and knowable by both the development applicant or proponent and the public official,” as California Government Code §65589.5(h)(9) states.

A few days later, the City received a second letter citing the HAA, this time from the California Housing Defense Fund (CalHDF), a non-profit housing organization that uses legal advocacy to hold communities to state housing laws and their own zoning standards.

“Denial of this project based on the subjective findings of the Design Review Committee, which have no basis in the municipal code, exposes the City to a significant risk of litigation,” wrote CalHDF Executive Director Dylan Casey and Director of Planning and Investigations James M. Lloyd.

In a statement provided to the Outpost in advance of tomorrow’s meeting, Krikston wrote that Eureka’s own 2040 General Plan includes a strategy to “maximize potential of the few vacant and underutilized sites” and reiterated the proposal’s compliance with Eureka’s requirements for setbacks, height restrictions, parking and maximum units, as well as its desirable blend of Farmhouse and Craftsman-style design inspirations and modern sustainability features (“100% electric,” equipped with solar panels and electric vehicle charging).

“In the past 9 years, ACGC has completed 30 residential units through in-fill projects that transform underutilized property into homes for our community as a key part of these same housing goals set by the city,” Krikston wrote in the provided statement, “These apartments are occupied 99% of the time and demonstrate the need for middle-range housing for Eureka’s workforce, students, seniors and families.”

CalHDF’s May 23 letter also included what it termed the “public benefits” of ACGC’s proposal, such as growth to Eureka’s tax base and reduced competition for existing housing stock in the city.

Staff are recommending that the Planning Commission reverse the Design Review Committee’s denial of the project, provide conditional approval for the project and adopt a resolution confirming the City’s determination that the proposed project is categorically exempt from the provisions of the California Environmental Quality Act (CEQA) in tomorrow’s meeting.

###

Also at Tuesday’s meeting, the Commission will consider approving a Conditional Use Permit, Coastal Development Permit and Design Review for local developer Travis Schneider’s RV Park Project, which would create a new resort RV park between two City-owned parcels on Waterfront Drive. (For background, see an Outpost story from 2019 at this link.)

The meeting starts at 5:30 p.m., and the agenda can be found below. Original agenda in PDF form, along with remote participation instructions, can be found at this link..


Eureka Planning Commission
June 26, 2024, 5:30 p.m.

A. ROLL CALL

B. SALUTE TO THE FLAG

C. APPROVAL OF MINUTES

1. Planning Commission Meeting Minutes

DOCUMENTS:

Meeting Minutes.pdf


D. ORAL COMMUNICATIONS

E. PUBLIC HEARINGS - CONTINUED

F. PUBLIC HEARINGS - NEW

1. ACGC Five-Unit Multi-Family Residential Development Design Review (DR-24-0001) Appeal Location: Vacant lot one parcel west of the southwest corner of West Buhne Street and Garland

The Planning Commission is considering a proposal for a five-unit multi-family residential development on a vacant lot in the city. The Design Review Committee had initially denied the project due to concerns about its impact on neighbors, but the applicant is appealing that decision. The staff is recommending a public hearing to review the project and potentially approve it with some conditions. The project meets the city’s zoning and design standards, and the staff believes it should be approved. A decision will be made by July 4th.

— LoCOBot

… or, as a recipe!

Recipe Title: ACGC Five-Unit Multi-Family Residential Development

Ingredients:
- 9,000 square feet (0.21 acre) vacant parcel
- Three one-bedroom units
- Three two-bedroom units
- Three three-bedroom units
- Attached garages
- Long-term bicycle parking spaces
- Landscaping materials
- Fencing materials
- Paved driveway materials
- Waste storage screening materials
- Design Review Committee Resolution 2024-07

Instructions:
1. Prepare the 9,000 square feet vacant parcel by clearing and leveling the land.
2. Build a multi-family residential structure with a 3,494 square feet footprint.
3. Construct five two-story dwelling units - three one-bedroom units, three two-bedroom units, and three three-bedroom units.
4. Attach garages to each unit for parking.
5. Provide long-term bicycle parking spaces for residents.
6. Arrange landscaping around the property for aesthetic appeal.
7. Install fencing to create private outdoor spaces for each unit.
8. Create a shared paved driveway for access to the units.
9. Screen waste storage areas for a clean and organized appearance.
10. Review and consider Design Review Committee Resolution 2024-07 for any additional requirements or changes.
11. Ensure compliance with all design standards and criteria in EMC §155.412.040.
12. Hold a public hearing to gather feedback and input from the community.
13. Adopt a resolution finding the project exempt from CEQA and approving the construction of the ACGC five-unit multi-family residential development.
14. Serve hot and enjoy your new residential development!

— LoCOBot

DOCUMENTS:

Staff ReportAttachment 1 - Planning Commission ResolutionAttachment 2 - Submitted Plan SetAttachment 3 - Director AppealAttachment 4 - Staff Report for Design Review CommitteeAttachment 5 - Design Review Committee Resolution 2024-07Attachment 6 - Public Comment Received Prior to May 8, 2024 DRC MeetingAttachment 7 - Public Comment Received After Appeal Filed May 16, 2024


2. Schneider RV Park Project Location: 1535 Waterfront Drive; APNs: 002-241-013, -007, and -006 (City of Eureka), and

3. 1535 Waterfront Drive Lot Line Adjustment and Street Vacation for Schneider RV Park Location: Lot Line Adjustment: Two City-owned parcels north of Waterfront Drive, to the west and north of

The City of Eureka wants to adjust the lot lines of two parcels and vacate parts of two streets to build an RV park. The project is part of a larger plan to develop the waterfront area. The proposal includes merging parcels, obtaining permits, and following environmental regulations. A public hearing will be held to discuss the project. The goal is to create a recreational area that promotes tourism and protects natural resources.

— LoCOBot

… or, as an episode of Seinfeld!

Title: The RV Park

[Jerry, Elaine, George, and Kramer are at Monk’s Cafe, discussing their upcoming weekend plans]

Jerry: So, what’s everyone up to this weekend?

Elaine: I’m thinking of heading out of town for a little camping trip. I found this great RV park up north near the waterfront.

George: RV park? That sounds like fun. I could use a weekend getaway.

Kramer: Oh, I love RV parks! They’re like little communities on wheels.

Jerry: Well, I guess camping is the thing to do this weekend. Maybe I’ll join you guys.

[Later that week, Jerry, Elaine, George, and Kramer arrive at the RV park near the waterfront. As they set up their campsite, they notice some construction happening nearby]

Jerry: What’s going on over there?

Elaine: Looks like they’re building something. Maybe some new amenities for the park?

George: I hope they have good bathrooms. I can’t stand roughing it in the woods.

Kramer: Oh, don’t worry, George. I’m sure they’ll have all the luxuries of home in this RV park.

[The group goes to the park office to inquire about the construction. They speak with Caitlin Castellano, the Senior Planner overseeing the project]

Elaine: Excuse me, what’s being built over there?

Caitlin: Oh, we’re making some adjustments to the lot lines and vacating portions of the streets to facilitate the development of the RV park.

Jerry: Lot lines and street vacations? Sounds complicated.

Caitlin: It’s all part of the process to improve and expand the park’s amenities for visitors. We’re also working on obtaining permits for a mixed-use development in the future.

George: Well, as long as I have a comfortable bed in my RV, I’m happy.

Kramer: I can’t wait to see how this park turns out. It’s going to be the best RV park in town!

[As the group settles in for the weekend, they enjoy the new amenities and explore the waterfront. They end the episode sitting around a campfire, sharing stories and enjoying the beauty of the RV park near the waterfront]

— LoCOBot

DOCUMENTS:

Staff ReportAttachment 1 - LLA ResolutionAttachment 2 - SV Resolution


G. DIRECTOR'S REPORTS AND COMMUNICATIONS

H. ADJOURNMENT