Power Outage in Pine Hills
Updates from PG&E
3:15 p.m.
Started | Wednesday, March 2, 2016 @ 3 p.m. |
Customers affected | 48 |
Cause | Unknown - PG&E is investigating the cause. |
PG&E status | PG&E is assessing the cause at the outage location. |
PG&E ETA | 3:54 p.m. |
Estimated time of restoral | Wednesday, March 2, 2016 @ 5 p.m. |
4:15 p.m.
Customers affected | 22 |
4:43 p.m.
Customers affected | 12 |
Estimated time of restoral | Wednesday, March 2, 2016 @ 11:59 p.m. |
5:03 p.m.
Customers affected | Six |
5:27 p.m.
Customers affected | Two |
5:47 p.m.
Cause | Found damage to underground equipment. |
PG&E ETA | 3:39 p.m. |
6:14 p.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
6:40 p.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
Estimated time of restoral | Thursday, March 3, 2016 @ 2 a.m. |
2:08 a.m.
Estimated time of restoral | Thursday, March 3, 2016 @ 5 a.m. |
5:14 a.m.
Estimated time of restoral | Thursday, March 3, 2016 @ 8 a.m. |
6:17 a.m.
PG&E status | Power restored. |