Power Outage in Bridgeville
Updates from PG&E
6:16 p.m.
Started | Saturday, March 5, 2016 @ 6:16 p.m. |
Customers affected | One |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
6:59 p.m.
Customers affected | Two |
8:20 p.m.
Started | Saturday, March 5, 2016 @ 6:11 p.m. |
Customers affected | 96 |
9:10 p.m.
PG&E status | PG&E is assessing the cause at the outage location. |
PG&E ETA | 8:19 p.m. |
9:30 p.m.
Customers affected | 14 |
9:49 p.m.
Cause | Trees are in contact with electrical equipment. |
PG&E status | PG&E repair crew is on-site working to restore power. |
PG&E ETA | 9:45 p.m. |
10:01 p.m.
Estimated time of restoral | Sunday, March 6, 2016 @ 4 a.m. |
10:36 p.m.
Estimated time of restoral | Sunday, March 6, 2016 @ 7 a.m. |
4:47 a.m.
PG&E status | Power restored. |