Power Outage in McKinleyville
Updates from PG&E
5:23 p.m.
Started | Wednesday, April 13, 2016 @ 5:23 p.m. |
Customers affected | One |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Wednesday, April 13, 2016 @ 9 p.m. |
8:20 p.m.
Cause | Unknown - PG&E is investigating the cause. |
PG&E status | PG&E is assessing the cause at the outage location. |
PG&E ETA | 8:36 p.m. |
8:35 p.m.
Customers affected | Nine |
Cause | Field personnel have found a downed power line. |
8:42 p.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
8:54 p.m.
Estimated time of restoral | Thursday, April 14, 2016 @ 2 a.m. |
11:22 p.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
PG&E ETA | 11:45 p.m. |
2:02 a.m.
PG&E status | Power restored. |