Power Outage in Myrtletown
Updates from PG&E
1:18 a.m.
Started | Saturday, April 23, 2016 @ 1:16 a.m. |
Customers affected | 10 |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Saturday, April 23, 2016 @ 4:30 a.m. |
1:38 a.m.
Cause | Unknown - PG&E is investigating the cause. |
PG&E status | PG&E is assessing the cause at the outage location. |
PG&E ETA | 2:02 a.m. |
1:42 a.m.
Cause | There is a problem with the transformer. |
2:19 a.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
4:13 a.m.
Estimated time of restoral | Saturday, April 23, 2016 @ 11 a.m. |
8:25 a.m.
PG&E ETA | 10 a.m. |
Estimated time of restoral | Saturday, April 23, 2016 @ 1 p.m. |
9:12 a.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
10:52 a.m.
PG&E status | Power restored. |