Power Outage in Myrtletown
Updates from PG&E
5:22 a.m.
Started | Tuesday, June 30, 2015 @ 5:22 a.m. |
Customers affected | 30 |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Tuesday, June 30, 2015 @ 8:30 a.m. |
5:31 a.m.
PG&E status | PG&E assessment crew is en route to the outage. |
PG&E ETA | 6:16 a.m. |
5:59 a.m.
Cause | Unknown - PG&E is investigating the cause. |
PG&E status | PG&E is assessing the cause at the outage location. |
6:42 a.m.
Cause | There is a problem with the transformer. |
6:53 a.m.
Customers affected | Two |
PG&E status | PG&E is sending a repair crew to the outage location. |
7:29 a.m.
PG&E ETA | 9 a.m. |
Estimated time of restoral | Tuesday, June 30, 2015 @ 11 a.m. |
7:44 a.m.
7:45 a.m.
PG&E ETA | 9 a.m. |
9:05 a.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
10:52 a.m.
PG&E status | Power restored. |