Power Outage in Ferndale
Updates from PG&E
8:20 p.m.
Started | Wednesday, Nov. 16, 2016 @ 8:12 p.m. |
Customers affected | One |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Wednesday, Nov. 16, 2016 @ 11:15 p.m. |
9:07 p.m.
Cause | Unknown - PG&E is investigating the cause. |
PG&E status | PG&E is assessing the cause at the outage location. |
PG&E ETA | 9:31 p.m. |
9:49 p.m.
Cause | PG&E staff have found a connection in need of repair. |
11:18 p.m.
Started | Wednesday, Nov. 16, 2016 @ 7:45 p.m. |
Customers affected | 16 |
Estimated time of restoral | Thursday, Nov. 17, 2016 @ 2 a.m. |
2:17 a.m.
Cause | Field personnel have found a downed power line. |
Estimated time of restoral | Thursday, Nov. 17, 2016 @ 7 a.m. |
2:38 a.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
3:10 a.m.
PG&E status | PG&E repair crew is en route to the outage location. |
PG&E ETA | 4:30 a.m. |
6:42 a.m.
PG&E status | Power restored. |