Power Outage in Garberville

Updates from PG&E

9:56 p.m.

StartedMonday, Jan. 2, 2017 @ 9:50 p.m.
Customers affected136
CauseUnknown - PG&E will be assessing the cause.
PG&E statusPG&E has assigned a crew to assess the outage.

11:50 p.m.

PG&E statusPG&E assessment crew is en route to the outage.
PG&E ETA12:26 a.m.

12:24 a.m.

PG&E statusPG&E is assessing the cause at the outage location.

1:24 a.m.

Estimated time of restoralTuesday, Jan. 3, 2017 @ 5 a.m.

2:24 a.m.

Customers affected21

3:43 a.m.

CauseField personnel have found a downed power line.
PG&E statusPG&E repair crew is on-site working to restore power.

5:07 a.m.

PG&E statusPower restored.