Power Outage in Willow Creek
Updates from PG&E
1:03 a.m.
Started | Monday, March 6, 2017 @ 1:02 a.m. |
Customers affected | One |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Monday, March 6, 2017 @ 6:15 a.m. |
1:07 a.m.
Started | Monday, March 6, 2017 @ 1 a.m. |
Customers affected | 151 |
1:39 a.m.
Cause | Unknown - PG&E is investigating the cause. |
PG&E status | PG&E is assessing the cause at the outage location. |
PG&E ETA | 1:45 a.m. |
2:32 a.m.
PG&E status | PG&E has assigned a crew to assess the outage. |
2:41 a.m.
Cause | Trees are in contact with electrical equipment. |
PG&E status | PG&E is assessing the cause at the outage location. |
2:52 a.m.
PG&E status | Power restored. |