Power Outage in McKinleyville
Updates from PG&E
8:43 a.m.
Started | Friday, Aug. 21, 2015 @ 8:35 a.m. |
Customers affected | 101 |
Cause | Planned maintenance in the area. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Friday, Aug. 21, 2015 @ 5 p.m. |
3:31 p.m.
Started | Monday, March 22, 2021 @ 3 p.m. |
Customers affected | 12 |
Cause | Our preliminary determination is that your outage was caused by an equipment issue. |
Estimated time of restoral | Monday, March 22, 2021 @ 10 p.m. |
3:42 p.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
3:47 p.m.
PG&E ETA | 5 p.m. |
9:45 p.m.
PG&E status | PG&E repair crew is en route to the outage location. |
PG&E ETA | 5:30 p.m. |
Estimated time of restoral | Tuesday, March 23, 2021 @ 8 a.m. |
2:22 a.m.
PG&E status | Power restored. |