Power Outage in Bridgeville
Updates from PG&E
12:02 a.m.
Started | Tuesday, June 13, 2017 @ 11:51 p.m. |
Customers affected | One |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E assessment crew is en route to the outage. |
Estimated time of restoral | Wednesday, June 14, 2017 @ 4 a.m. |
1:51 a.m.
Cause | Unknown - PG&E is investigating the cause. |
PG&E status | PG&E is assessing the cause at the outage location. |
3:03 a.m.
Customers affected | Two |
Cause | There is a problem with the transformer. |
3:38 a.m.
Estimated time of restoral | Wednesday, June 14, 2017 @ noon |
3:39 a.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
8:43 a.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
PG&E ETA | 8:45 a.m. |
11:01 a.m.
Estimated time of restoral | Wednesday, June 14, 2017 @ 2 p.m. |
11:47 a.m.
PG&E status | Power restored. |