Power Outage in Westhaven-Moonstone

Updates from PG&E

8:59 p.m.

StartedThursday, Aug. 31, 2017 @ 8:58 p.m.
Customers affected18
CauseUnknown - PG&E will be assessing the cause.
PG&E statusPG&E has assigned a crew to assess the outage.
Estimated time of restoralFriday, Sept. 1, 2017 @ 12:30 a.m.

9:08 p.m.

PG&E statusPG&E assessment crew is en route to the outage.
PG&E ETA9:38 p.m.

9:15 p.m.

9:41 p.m.

CauseUnknown - PG&E is investigating the cause.
PG&E statusPG&E is assessing the cause at the outage location.

10:28 p.m.

CauseField personnel have found a downed power line.

10:49 p.m.

PG&E statusPG&E is sending a repair crew to the outage location.

12:05 a.m.

PG&E statusPG&E repair crew is on-site working to restore power.
Estimated time of restoralFriday, Sept. 1, 2017 @ 5 a.m.

6:12 a.m.

PG&E statusPower restored.