Power Outage in Arcata
Updates from PG&E
10:24 a.m.
Started | Saturday, Jan. 5, 2019 @ 10:24 a.m. |
Customers affected | Five |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
10:29 a.m.
Started | Saturday, Jan. 5, 2019 @ 9:43 a.m. |
Customers affected | 234 |
PG&E status | PG&E is assessing the cause at the outage location. |
10:43 a.m.
11:07 a.m.
Customers affected | Two |
11:13 a.m.
Cause | Our preliminary determination is that your outage was caused by an equipment issue. |
11:34 a.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
12:03 p.m.
PG&E ETA | 3 p.m. |
12:34 p.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
Estimated time of restoral | Saturday, Jan. 5, 2019 @ 3:30 p.m. |
1:19 p.m.
Estimated time of restoral | Saturday, Jan. 5, 2019 @ 5 p.m. |
4:17 p.m.
PG&E status | Power restored. |