Power Outage in Bridgeville
Updates from PG&E
3:21 a.m.
Started | Sunday, Feb. 10, 2019 @ 3:16 a.m. |
Customers affected | 73 |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
6:06 p.m.
Customers affected | 71 |
9:02 a.m.
11:17 a.m.
Cause | Our preliminary determination is that your outage was caused by an equipment issue. |
PG&E status | PG&E is sending a repair crew to the outage location. |
PG&E ETA | 1 p.m. |
Estimated time of restoral | Monday, Feb. 11, 2019 @ 6 p.m. |
11:26 a.m.
Customers affected | 69 |
2:36 p.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
5:28 p.m.
Customers affected | 61 |
6:01 p.m.
Estimated time of restoral | Monday, Feb. 11, 2019 @ 11 p.m. |
6:13 p.m.
Estimated time of restoral | Tuesday, Feb. 12, 2019 @ 3 p.m. |
8:19 a.m.
Estimated time of restoral | Tuesday, Feb. 12, 2019 @ 8 p.m. |
7:07 p.m.
Estimated time of restoral | Wednesday, Feb. 13, 2019 @ 8 p.m. |
8:59 a.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
7:18 p.m.
PG&E status | Power restored. |