Power Outage in Bridgeville
Updates from PG&E
1:21 p.m.
Started | Thursday, Feb. 14, 2019 @ 11:35 a.m. |
Customers affected | Two |
Cause | Our preliminary determination is that your outage was caused by an equipment issue. |
PG&E status | PG&E is assessing the cause at the outage location. |
PG&E ETA | 1:36 p.m. |
1:34 p.m.
Estimated time of restoral | Thursday, Feb. 14, 2019 @ 6 p.m. |
1:38 p.m.
PG&E status | PG&E repair crew is en route to the outage location. |
PG&E ETA | 2:30 p.m. |
3:35 p.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
Estimated time of restoral | Thursday, Feb. 14, 2019 @ 8 p.m. |
4:40 p.m.
Estimated time of restoral | Thursday, Feb. 14, 2019 @ 10 p.m. |
5:09 p.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
5:34 p.m.
PG&E status | Power restored. |