Power Outage in Arcata
Updates from PG&E
9:45 a.m.
Started | Tuesday, March 5, 2019 @ 8:26 a.m. |
Customers affected | Seven |
Cause | Our preliminary determination is that your outage was caused by an equipment issue. |
PG&E status | PG&E is assessing the cause at the outage location. |
Estimated time of restoral | Tuesday, March 5, 2019 @ noon |
9:48 a.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
10:28 a.m.
PG&E ETA | 2 p.m. |
Estimated time of restoral | Tuesday, March 5, 2019 @ 6 p.m. |
1:03 p.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
2:12 p.m.
PG&E status | Power restored. |