Power Outage in Ferndale
Updates from PG&E
3:06 p.m.
Started | Thursday, Oct. 8, 2015 @ 3:06 p.m. |
Customers affected | One |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Thursday, Oct. 8, 2015 @ 6:15 p.m. |
3:53 p.m.
PG&E status | PG&E assessment crew is en route to the outage. |
PG&E ETA | 4:53 p.m. |
4:57 p.m.
Cause | PG&E staff have found a connection in need of repair. |
PG&E status | PG&E is assessing the cause at the outage location. |
5:30 p.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
5:55 p.m.
PG&E status | PG&E repair crew is en route to the outage location. |
6:20 p.m.
Estimated time of restoral | Thursday, Oct. 8, 2015 @ 11:59 p.m. |
8:20 p.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
10:07 p.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
10:27 p.m.
PG&E status | Power restored. |