Power Outage in Bridgeville

Updates from PG&E

7:10 a.m.

StartedSaturday, May 18, 2019 @ 7:05 a.m.
Customers affected104
CauseOur preliminary determination is that your outage was caused by scheduled maintenance work.
PG&E statusPG&E has assigned a crew to assess the outage.
Estimated time of restoralSaturday, May 18, 2019 @ 8 p.m.

7:19 a.m.

PG&E statusPG&E repair crew is on-site working to restore power.

5:42 p.m.

PG&E statusPower restored.