Power Outage in Bridgeville
Updates from PG&E
4:24 a.m.
Started | Friday, Feb. 7, 2020 @ 4:08 a.m. |
Customers affected | 61 |
Cause | Unknown - PG&E will be assessing the cause. |
PG&E status | PG&E has assigned a crew to assess the outage. |
Estimated time of restoral | Friday, Feb. 7, 2020 @ 9 a.m. |
6:02 a.m.
Cause | PG&E is investigating the cause of your outage. |
PG&E status | PG&E is assessing the cause at the outage location. |
6:35 a.m.
Customers affected | 24 |
Cause | Our preliminary determination is that your outage was caused by an equipment issue. |
6:45 a.m.
Customers affected | 21 |
7:25 a.m.
Customers affected | 17 |
7:32 a.m.
PG&E status | PG&E is sending a repair crew to the outage location. |
7:37 a.m.
Estimated time of restoral | Friday, Feb. 7, 2020 @ 4 p.m. |
9:24 a.m.
PG&E status | PG&E repair crew is on-site working to restore power. |
PG&E ETA | 9:30 a.m. |
1:12 p.m.
PG&E status | Power restored. |