Power Outage in Bridgeville
Updates from PG&E
5:22 a.m.
Started | Monday, Dec. 27, 2021 @ 2:46 a.m. |
Customers affected | 50 |
Cause | Unknown - PG&E will be assessing the cause. |
8:52 a.m.
Cause | PG&E is investigating the cause of your outage. |
12:02 p.m.
Customers affected | 48 |
Cause | Our preliminary determination is that your outage was caused by an equipment issue. |
Estimated time of restoral | Monday, Dec. 27, 2021 @ 5 p.m. |
4:52 p.m.
Estimated time of restoral | Tuesday, Dec. 28, 2021 @ noon |
12:32 p.m.
Estimated time of restoral | Wednesday, Dec. 29, 2021 @ 3 p.m. |
8:12 p.m.
Customers affected | 46 |
10:12 a.m.
PG&E status | Power restored. |