Power Outage in Somes Bar
Updates from PG&E
8:42 p.m.
Started | Monday, Dec. 19, 2022 @ 5 p.m. |
Customers affected | 25 |
Cause | |
Estimated time of restoral | Monday, Dec. 19, 2022 @ 9:45 p.m. |
8:52 p.m.
Started | Monday, Dec. 19, 2022 @ 2:06 p.m. |
Customers affected | 26 |
Estimated time of restoral | Monday, Dec. 19, 2022 @ 10:45 p.m. |
9:22 p.m.
Cause | PATROLLING |
10:52 p.m.
Cause | BRKN UG EQUIPMNT |
Estimated time of restoral | Tuesday, Dec. 20, 2022 @ 3:45 p.m. |
5:22 a.m.
Estimated time of restoral | Tuesday, Dec. 20, 2022 @ 10 p.m. |
6:12 p.m.
PG&E status | Power restored. |