Power Outage in Fernwood
Updates from PG&E
6:32 p.m.
Started | Tuesday, Sept. 3 @ 6:08 p.m. |
Customers affected | 130 |
Cause | PATROLLING |
6:52 p.m.
Estimated time of restoral | Wednesday, Sept. 4 @ 12:45 a.m. |
12:22 a.m.
Customers affected | 128 |
12:52 a.m.
Estimated time of restoral | Wednesday, Sept. 4 @ 2:45 a.m. |
2:32 a.m.
Estimated time of restoral | Wednesday, Sept. 4 @ 2 p.m. |
1:52 p.m.
Cause | BRKN POLE EQUIPMNT |
Estimated time of restoral | Wednesday, Sept. 4 @ 5 p.m. |
5:02 p.m.
Estimated time of restoral | Thursday, Sept. 5 @ 12:01 a.m. |
6:02 p.m.
Customers affected | 127 |
7:22 p.m.
Customers affected | 126 |
7:32 p.m.
Customers affected | 122 |
8:22 p.m.
Customers affected | 98 |
8:52 p.m.
Customers affected | Two |
9:52 p.m.
Estimated time of restoral | Thursday, Sept. 5 @ 3 a.m. |
1:22 a.m.
Cause | REPLCE TXFMR |
Estimated time of restoral | Thursday, Sept. 5 @ 4 a.m. |
3:02 a.m.
PG&E status | Power restored. |