Power Outage in Trinidad
Updates from PG&E
9:32 a.m.
Started | Tuesday, April 22 @ 9:15 a.m. |
Customers affected | Four |
Cause | PLNND SHUTDOWN |
Estimated time of restoral | Tuesday, April 22 @ 3 p.m. |
2:52 p.m.
Estimated time of restoral | Tuesday, April 22 @ 4:30 p.m. |
3:32 p.m.
PG&E status | Power restored. |