Power Outage in Maple Creek
Updates from PG&E
10:32 a.m.
| Started | Wednesday, May 14 @ 10:09 a.m. |
| Customers affected | 149 |
| Cause |
10:52 a.m.
| Customers affected | 13 |
| Cause | PLNND SHUTDOWN |
| Estimated time of restoral | Wednesday, May 14 @ 4:30 p.m. |
10:52 a.m.
| Customers affected | 41 |
| Cause | |
| Estimated time of restoral | Wednesday, May 14 @ 4:15 p.m. |
11:52 a.m.
| Cause | PATROLLING |
2:52 p.m.
| Customers affected | 23 |
4:22 p.m.
| Estimated time of restoral | Wednesday, May 14 @ 6:15 p.m. |
5:22 p.m.
| PG&E status | Power restored. |